Question:
Which of the following documents is not used as input for the validate scope process? 11 o The project management plan, containing the scope baseline consisting of the project scope statement and its associated WBS and WBS dictionary. o The validated deliverables, completed and checked for correctness by the Perform quality control process. o The requirements traceability matrix, linking requirements to their origin and tracing them throughout the project lifecycle. o The RACI matrix, describing accountabilities in case of product rejection.