estimation of current cost Engineering Economics Analysis Question

| June 8, 2016

Question
A manufacturer decides to sell products at a per-unit price of $150. The per-unit material cost was $50 a year ago when the material cost index was 100. The current material cost index is 125. The products are being made by a machine that currently costs $100,000 and produces a 1000 units during its…